Allianz Parque pitch inspected by FIFA, Palmeiras await green light

In partnership with
Yahoo sportsGazeta Esportiva.com
·5 de marzo de 2026

The Palmeiras is close to being able to return to the Allianz Parque. The new synthetic turf of Verdão's stadium underwent the necessary tests this week, in an evaluation conducted by a laboratory authorized by FIFA, which will release the results in the coming days.
After the works, which began in December, the Palmeiras stadium now features the seventh generation of synthetic grass, the most modern technology of artificial surfaces for high-performance sports, complying with the manual of the football's governing body.
The process, which lasted about seven hours, marks the end of the field's renovation.
Before the start of every season, a laboratory authorized by FIFA conducts an analysis of the synthetic turf at Allianz Parque, something specific due to the use of artificial grass. This does not occur on natural grass fields.
The tests aim to ensure that the field provides the best playing conditions for the competitions held at the arena. Among the topics evaluated during the process are leveling, impact cushioning, ball roll, ball bounce, traction, and rotational resistance.
Without Allianz Parque available, Palmeiras played as the home team at Arena Crefisa Barueri. However, Abel Ferreira's team now has a scheduled date to debut at their home. The first game at Allianz Parque will take place on the 15th, against Mirassol, for the Brasileirão, starting at 6:30 PM (Brasília time).
Palmeiras and WTorre invested R$ 11 million in replacing the surface of Allianz Parque, from purchasing materials to completing the work. After receiving the Quality Pro certificate from FIFA, Palmeiras will return to the stadium for the continuation of the season, with games from the Brasileirão, Copa do Brasil, and Libertadores.
The new synthetic turf at Allianz Parque was supplied by Soccer Grass, responsible for the field since 2020. Initially, the cork and sand were removed, the grass was taken out, and the drainage branches were opened.
Subsequently, the filling residues were removed, the gravel layer was leveled and compacted, the shock pad rolls were opened, the carpets were installed, and the sand was spread and distributed, along with the field marking and other installations. There was also an update to the drainage system.