Inside the plans to expand La Bombonera to 80,000 fans

In partnership with
Yahoo sportsLa Número 12
·10 de marzo de 2026

Boca presented a document detailing the project to expand La Bombonera and increase its capacity to 80,000 spectators. Below, we share it as it was presented:
The expansion of La Bombonera is not a recent idea nor an isolated announcement.
It is the result of more than two years of technical, legal, and structural work.
Since the beginning of the management, more than 60 projects have been executed and are underway within the stadium and its surroundings, many of which are part of the comprehensive plan leading to the final expansion.
La Bombonera is not being relocated.
A new stadium is not being built.
It is being expanded while respecting its identity.
The Bombonera expansion project is structured around six main axes:
1. Completed and ongoing works
More than 60 interventions carried out in the stadium and its surroundings to prepare the necessary infrastructure for the expansion.
2. Situation of neighboring homes and legal framework
Analysis of the urban environment and the regulatory framework that conditions the project's development.
3. Bombonera expansion project
Description of the projected interventions to expand the stadium's capacity while respecting its identity and current regulations.
4. Towers over the railway sector and fourth tier
First executive stage of the project, currently under technical evaluation by railway organizations.
5. Structural study of the stadium
Technical analysis carried out by specialist engineers that validates the structural capacity for the expansion.
6. Technical documentation of the project
Complete development of plans, reports, and studies necessary for the project's execution.
Before developing the expansion project, the Club initiated a process of recovery, organization, and modernization of the stadium.
For more than two years, over 60 projects have been executed and are underway within La Bombonera and its operational areas.
Many of these interventions are not visible from the stands but are fundamental to preparing the stadium's infrastructure for its growth.
Work has been done on:
INFRASTRUCTURE AND LIGHTING
For years, the stadium grew with added installations without planning: visible cables, exposed pipes, old electrical systems.
For more than two years, comprehensive organization has been underway:
MAIN ENTRANCE – DOORS 1 TO 5 (BRANDSEN 805)

The entire front of the club is being remodeled from Door 1 to Door 5.
At Door 3 (main), a new structure of over 200 m² is being built to expand the entrance hall.
Includes:
CENTRAL HALL – INSTITUTIONAL ENTRANCE (over 400 m²)
Comprehensive renovation of the internal entrance space:
MEMBER DEPARTMENT AND SERVICE CENTER (over 300 m²)
Complete transformation of the service area:
RENOVATION OF HALLWAYS AND STAIRS
Comprehensive renovation of:
FOOD COURT – MIDDLE STAND (1,800 m²)
Total renovation of the area:
NEW FOOD COURT STAND L (over 1,500 m² new – Under construction)
More than 5,000 people circulated through a corridor of just 1.5 meters.
The area is expanded to a space up to 13 meters wide.
Includes:
NORTH AND SOUTH STANDS
Construction of four new food stalls (two in each sector).
Modern and safe facilities for members attending the popular stands.
PARKING AND LOGISTICS
Parking 2
More than 7,800 m² of new internal roads.
Capacity expanded to over 200 parking spaces.
Parking 3
Improvements in lighting, enclosures, and paving.
Projected capacity from 600 to 900 vehicles.
A new transmission center will be built there.
Parking 86
Total recovery of 4,000 m² of abandoned space.
New garages, kitchens, and services.
Upcoming construction of an accreditation building.
PARKING 1 AND TRANSMISSION CENTER
Today, Parking 1 operates improvised for television, with cables and equipment visible.
The operation is moved to a fixed center in Parking 3 with underground connections.
This frees up Parking 1 to become a promenade and to place four vertical circulation towers there, a key piece of the expansion.
PLAYER ENTRANCE AND MIXED ZONE
Total renovation of the area:
GYM FOR MEMBERS – BRANDSEN 842 (1,500 m² - Under construction)
Construction of a modern gym over an old unused warehouse.
Conclusion:
The expansion is already underway.
First, the base was organized, recovered, and modernized.
Work was done on infrastructure, circulation, services, and safety to prepare the stadium for growth.
Before defining the own expansion project —which was developed over more than two years— a serious analysis was conducted on the feasibility of acquiring the homes facing the stadium.
This analysis included domain reports and the study of the current legal framework.
Current regulatory framework
Through Law No. 6,922 (File 2693-J-2024), called "Update of the Catalog of Protected Properties of the Urban Code," properties were added to the list of heritage protection of the City.
In Article 3 of this law, properties are cataloged that cannot be freely demolished or modified.
Impact on the adjoining half-blocks
In the two half-blocks often mentioned as an expansion alternative, there are:
Besides the heritage issue
From the analysis of the domain reports, it emerges that a significant percentage of the properties present situations such as:
Conclusion
The stadium's expansion cannot be based on 48 individual negotiations, many of them conditioned by legal restrictions and judicial situations.
Therefore, it was decided to move forward with an own project:
After conducting various technical, legal, and structural analyses, President Juan Román Riquelme conveyed a clear premise to the Club's team of architects and engineers:
"Let's work on our own project. Within La Bombonera. Without touching houses. Without violating the code. And respecting its identity."
That was the directive.
Do not move the stadium.
Do not build a new one.
Do not forgo its essence.
Expand La Bombonera without ceasing to be La Bombonera.
From that definition, the comprehensive project was developed, which includes:
1) Expansion over Iberlucea – Final closure of the stadium

The demolition of the current boxes over Iberlucea is projected to generate the stadium's final closure.
In that sector, the following are built:
2) Construction of a Fourth Tier
A fourth level of stands is added, replicating the development of the current third tier.

This allows:
3) Roof Covering
A complete roof is projected over the four stands.
This will allow:
4) Towers and bridges over the railway sector (Parking 1)

Four vertical circulation towers are projected in Parking I:
5) Door 18: Reconfiguration

The two current elevators are replaced by a new tower with six elevators of greater capacity and better features.
This new tower reaches the fourth tier and significantly improves accessibility.
6) Shifting the playing field
To generate the necessary width for the new stand over Iberlucea, the playing field is projected to shift four meters towards the railway sector.
The field's height level is not modified.
A perimeter trench is created along the entire field contour, located next to the stands, intended for security personnel during events.
7) New FIFA Access and reorganization at field level
A single central access at field level is projected, allowing:
8) Expansion of the lower North and South stands
The slope of both popular stands is modified to:
Visual study (isoptic)
A complete visual study was conducted from all points of the stadium, including the new projected stands.
It implies that:
CLUB MESSAGE:
"The first stage has a completed executive project, presented and approved by FERROSUR ROCA S.A., and is currently submitted to the CNRT for technical evaluation. The corresponding validation is awaited to start the work."
Before presenting the expansion project, the Club commissioned a specific structural study on La Bombonera.
It is not a drawing.
It is not an idea.
It is a technical work developed by specialized structural engineers, with a descriptive report and professional analysis.
Studies were conducted on:
NOTE:
"The expansion has a structural study. Tests, concrete analysis, and technical verification were done. It is not a campaign drawing; it is a project with engineering."
(Suitable for submission to the City Government)
The expansion project is not a conceptual idea nor a render.
It has developed technical documentation ready to be submitted to the relevant authorities.
Includes:
What does this mean?
That the project:
CLOSURE
The expansion is projected with real technical basis, within the current code, and with documentation prepared for formal approval.
La Bombonera is not moving. It is expanding.