OffsAIde
·11 de julio de 2026
Nou Mestalla facade taking shape as roof works progress

In partnership with
Yahoo sportsOffsAIde
·11 de julio de 2026

Nou Mestalla's facade is being transformed as the project moves forward, with roof and interior works advancing.
According to AS, the compression ring has been installed, and radial cables that will support the roof are being deployed.
Auxiliary scaffolding for the traction ring cables has been completed, and protections across the stands have advanced to enable radial cable deployment.
The structure features 50 S355 steel pillars, with activity focused on the facade, staircase towers and several internal zones.
A panoramic view of Valencia now has Nou Mestalla as a prominent feature, as construction maintains a good pace.
Source: AS